Today we were made aware of significant damage to both the east and west gates and ADAM LLC is looking into getting it fixed ASAP. Although we know who damaged the west gate, we do not know who damaged the east gate. If anyone has any information, please let us know! Also, as a reminder,…
The east gate is again experiencing problems with the remote entry clickers. Signal Gate has been notified of the problem and an open ticket has been established. Hopefully, this issue will be resolved in the next 24 hours. We appreciate your patience and understanding as we once again attempt to remedy the issues on the…
We received notice minutes ago that Bates Paving & Sealing can perform the crack sealing on our roadways tomorrow Friday April 1st. Bates will begin the process at 7am and complete by 3pm. They will be starting at the East end of Sonoran Vista Trail in the right lane. They will work one traffic lane at…
Bates Paving & Sealing completed the asphalt removal and replacement at several locations on Sonoran Vista Trail, low area and east roundabout and at the East Gate entrance. Unfortunately at the West Gate, the contractor ran out of asphalt. You will notice a slight depression in the two cut areas. They will be back to complete this work…
Hello everyone! We realize the gate fixes and line striping seems to be taking a very long time, so we wanted t provide an update on each… Gate Fixing: We are currently in contact with various contractors to receive bids and we are also in the process of contacting our insurance company to discuss options….
The East Gate tree has been resolved. The tree was successfully removed by Branching Out Tree Service on the morning of February 25th, 2020. A copy of the contract can be found here – payment was issued via Pinehurst Properties.